the instrumentation specifically needed for the technical
operation of determining the critical mass. Secondly, the
instrumentation required from the viewpoint of possible hazards
which might arise from some accidental occurrence.
The instrumentation falling in the first category is as follows-
| 1. U235 pulse channel | ||
| 2. BF3 " " | ||
| 3. BF3 " " | These have sluggish level trips | |
| 4. BF3 " " | ||
| 5. B10 integrating channel | ||
| 6. B10 " " | These have fast level trips and are the primary safeties | |
| 7. [gamma] " " | ||
| 8. Liquid level indicator | ||
| 9. Rod and shim position indicators | ||
| 10. Sampling and liquid transfer device | ||
| 11. Monitoring systems for the critical procedures | ||
| a. [alpha] monitor | ||
| b. air monitor | ||
| c. personnel monitors - | film n sensitive | |
| film [beta], [gamma] sensitive | ||
| dosimeter n sensitive | ||
| dosimeter [beta], [gamma] sensitive | ||
In the second classification we have the following-

Below are listed partial cost estimates-
| 1. | U235 pulse chamber | cost information unavailable | |
| 120. | |||
| " " 204B | 395. | ||
| " " 1010 scaler | 430. | ||
| " " 410 rate meter | 325. | ||
| Keleket timer | 60. | ||
| Cable and connectors | (50) | ||
| Level trip modification | (100) | ||
| 2. | BF3 | 130 or 105. | |
| 525. | |||
| 325. | |||
| Cable and connectors | (50) | ||
| Level trip modification | (100) | ||
| 3. | Duplicate of 2 | ||
| 4. | Duplicate of 2 except omit ratemeter | ||
| 5. | B10 ionization chamber | (400) | |
| Shop estimate from | (100) | ||
| Quartz insulation from | (100) | ||
| Special alloy materials | (100) | ||
| Special B10 coating.. requires special induction heating with inter gas flow. It may be advisable to make arrangements with chambers. This cost cannot be estimated. |
|||
| Pre amp | (250) | ||
| Level trip | (100) | ||
| Difference amp | (50) | ||
| Cabling | (200) | ||
| Pure lead shield | (50) | ||
| 6. | Duplicate of 5 except add 3 motors | 105. | |
| 7. Scintillation [gamma] channel. This has not been studied with sufficient care to make a sound estimate but it that it will be of the order of | (1000) | ||
| 8. | Liquid level indicator (see | ||
| 9. | Rod and shim position indicators approximately total | (50) | |
| 10. | Sampling and liquid transfer (see | ||
| 11. | Monitoring for critical procedures | ||
| 2 [alpha] Zeuto | 750 | ||
| air monitor | (100) | ||
| personnel monitor per person | |||
| 2 film badge | 10. | ||
| 2 dosimeters [beta], [gamma] | 25. | ||
| " neutron | 50. | ||
| use reading devices already have | |||

| 1. Campus monitors installed in permanent | (1200) | |
| 2. Stack monitor | (1000) | |
| 3. Dust monitor | (200) | |
| 4. mobile monitor | no estimate | |
| 5. Alarm system | no estimate | |
| (6. Console | no estimate ) | |
| 7. Liquid monitor | (2500) | |
| 8. Log channel | submitted to | ? |
| 9. Indium foils | no estimate | |
| 10. Recombiner and disposal system ( |
||
| 11. Gas masks | (300) | |
| General | ||
| Interlocks, light panel, and hook up | (1500) | |