Current Status of Construction on the Nuclear Reactor and the Nuclear Reactor Building at North Carolina State College, with photographic enclosures.

NCSC #54
CURRENT STATUS OF CONSTRUCTION
ON THE
NUCLEAR REACTOR AND THE
AT

CURRENT STATUS OF CONSTRUCTION
ON THE
NUCLEAR REACTOR AND THE
AT
The Nuclear Reactor Project at
two separate parts: (1) Construction of the Nuclear Reactor, and (2)
Construction of a
laboratories are to be housed.
At the outset, it was proposed that the Nuclear Reactor be constructed
(at an estimated cost of $150,000) in one of the buildings already existing
on the campus. A considerable portion of the design of the Reactor was
completed with this in mind. Later, through a generous gift of $200,000
from the
the
for the project. Availability of this specially designed building, contain-
ing associated laboratories and auxiliarly equipment, will increase tremendously
the value and usefulness of the project.
Thus chronologically, plans for the Reactor itself were developed well
in advance of those for the
that considerable delay was encountered in crystallizing the architectural

In view of this situation, request was made, and permission was granted,
for construction of the Reactor to get under way even before final details
of the building plans had been drawn. On
of the Reactor (and Building) site was started, and in June, 1951 the
foundations and the floor for the Reactor Room. When this work was completed,
the same company was requested to erect the concrete shielding of the Reactor
Assembly. Working at a rather slow pace, the shielding was completed in
December, 1951.
The first attached photograph shows the Reactor shielding structure
(essentially completed). This photograph was made in November, 1951.
The
tractors for the
was scheduled for completion in November, 1952.
It is significant to note that not a single delay in construction has
been encountered on this project because of material shortages or delayed
deliveries. High priorities, and even government directives, have been a
vailable at any time they have been needed to secure delivery; however,
there has been a shortage of labor, and the construction program appears to be
a month at least behind schedule.
The second attached photograph shows the
stage of construction. One section of the concrete wall of the octagonally-shaped

Since completion of the Reactor Shield, efforts on the Reactor itself
have gone toward collecting and testing components which will comprise the
working assembly. The actual installation and final testing cannot be ac-
complished until the building is finished. After the building is finished,
from three to six months will be required to bring the Reactor into full
operation.
As mentioned above, completion of the
for November, 1952. It is to be hoped that actual completion will be
achieved by this date or shortly thereafter.
Copies to:

