Timeline
March 2007
| March 12 |
The renovation is completed and the opening of the East Wing is celebrated with a weeklong series of activities encouraging students to explore the new learning spaces. |
January 2007
| Jan. 4 |
Renovations on the entire second floor are completed and pass inspection. |
December 2006
| Dec. 28 |
Wired furniture installation begins on the first floor. |
August 2006
| Aug. 4 |
The renovations on the western end of the second floor are completed and pass fire marshal inspection. |
June 2006
| June 1 |
The Special Collections Research Center's new staff area (and temporary reading room) on the ground floor opens. |
May 2006
| May 15 |
The Special Collections staff area on the ground floor is completed. |
February 2006
| Feb. 20 |
The third floor (Administration) is reoccupied. |
October 2005
| Oct. 28 |
Phase B (Mailroom/Facilities on the ground floor) is completed. |
September 2005
| Sept. 26 |
Second floor telecommunications work begins. |
| Sept. 19 |
Third floor window replacement and infrastructure upgrades begin. |
| Sept. 1 |
The mailroom on the ground floor is completed. |
June 2005
| June 28 |
Demolition begins on the first floor. |
| June 1 |
The construction area on the first floor is sealed off. |
April 2005
| April 28 |
Request for contract award. |
March 2005
| March 1 |
Construction bids are opened. |
January 2005
| Jan. 30 |
The Libraries re-advertises for construction bids. |
| Jan. 9 |
Advertisement for construction bids. |
December 2004
|
The Reference Desk and patron computers in the East Wing are dismantled and moved to new locations. [directions] [floor plans]. |
Construction Phasing
|